News
Birchwood Rd., Water & Sewer Work Wednesday Aug 16 7:30 AM
- Published: August 15, 2023
Update as of 5:00 PM - Public Works has started turning on the water. Work had progressed better than anticipated. If your water is at all cloudy, please run your faucet for a few minutes to clear it. Thank you all for your patience!
Update Status as of 4:10 PM - Public Works is continuing the progress on the sewer and water work on Birchwood Road and all is going well. However, it is taking a bit longer than expected. Public Works expects the repairs to last another 2 to possibly 3 hours. An update will be posted as the process is nearing completion. Thank you for your patience!
Notice from Public Works: The Oxford Public works team will be doing water and sewer work on Birchwood Road, tomorrow, Wednesday August 16, 2023, starting at 7:30 AM.
Detours will be in place. There will be expected water service interruptions through out the day.
The following streets should expect interruptions (Birchwood Road, Foundry Street, Handel Street, Station Street and surrounding areas).
Please use caution in the area.